Route 28/Main Street Water Main Replacement Updates

10-15 to 10-18

Night Road Work to begin 9/22/2019

MassDOT will be conducting work in your community in the near future. The following project information is being forwarded for distribution to appropriate Municipal Departments.

• For questions, please contact the District 5 Construction Office at 508-884-4281. Please direct all public questions and complaints to the District 5 Construction Office.

Project Location (City/Town): FALMOUTH

Estimated Start Date of Work: 9/22/19

Project Type: Asphalt Pavement Repairs and Improvements.

Description of Work: Milling 2 inch depth of existing asphalt and placing Hot Mix Asphalt overlay at the following locations: Route 28, On / Off ramps associated with Exits at Route-151 (Excluding Rt-28 SB On Ramp), Thomas Landers Road and Brick Kiln Road.

Contractor: Lawrence-Lynch Corp. (508)-548-1800

Hours of Operation (Day/Night): 8:30 PM – 5:30 AM

Description of Traffic Management: Temporary detours (see attached) and Lane restrictions controlled by Police Details.

Estimated Duration of Work: (3) Weeks, Commencing operations on Sunday night September 22nd; Weather permitting.


Road Detours